Pinned Tweet
During the September quarter, mobilisation to site commenced at our Waroona Renewable Energy Project, marking the transition from several years of development to the construction phase of Stage One.
Stage One comprises a 132MW solar facility and an 81.5MW (6.9-hour) battery energy storage system (BESS), designed to capture solar energy during the day and dispatch electricity into the grid during periods of high-value demand in the evenings. With all major equipment supply and construction contracts in place, first generation is scheduled for 2028.
Recent works carried out at Waroona include the establishment of the construction laydown area, installation of construction facilities, tree clearing within the 330Kv under cable route, commencement of topsoil removal bulk earthworks for the solar farm’s internal road network, and construction of the operation and maintenance compound pad.
Major construction works commencing soon will include field piling for installation of the single access tracking system, followed by installation of the photovoltaic modules and construction of the solar facility balance of plant, which is scheduled to commence in early 2027.
Beyond Stage One, we're progressing plans to develop Waroona into a multi-stage renewable energy hub, utilising our existing 830-hectare landholding and proximity to the South West Interconnected System (SWIS). We’re targeting a Stage Two development comprised of a 130MW solar facility, and an 80MW BESS (~8hrs).
📺 Watch our video below for an overview of the Waroona Renewable Energy Project and what's ahead.
$FHE
About 200 jobs will be created in the Shire of Waroona as work begins on Frontier Energy's $FHE $310m Waroona Renewable Energy Project, writes journalist Rose Patane in the Bunbury Herald 📰
1
114
Major construction is now underway at our Waroona Renewable Energy Project in Western Australia. Our CEO Adam Kiley @Soph_Investor caught up with @StockheadAU's Tylah Tully this week to discuss the project's recent progress and next steps.
"Things are ramping up very quickly," he says. "I'm down at site now every week or two, and it always amazes me how quickly this project is starting to take shape."
This month we also executed a Capacity Investment Scheme Agreement (CISA) with the Australian Government for Waroona's Stage One, one of the final conditions precedent for financial close of the $280m debt facility, expected imminently. The CISA, combined with WA’s Reserve Capacity Scheme, provides a minimum level of guaranteed revenue support for the project until 2042.
Watch the full interview below 📺
$FHE
On Friday, the commencement of major construction at our Waroona Renewable Energy Project Stage One was marked by a sod turning ceremony led by The Honourable Amber-Jade Sanderson MLA, Western Australia’s Minister for Energy and Decarbonisation, as well as The Honourable Josh Wilson MP, Federal Assistant Minister for Climate Change and Energy.
Also in attendance were major investors, Frontier directors, and representatives from various groups, including the Shire of Waroona, EPC contractors, Western Power and other key stakeholders.
Stage One of Waroona, fully funded, comprises a 132MW solar facility and an 81.5MW battery energy storage system, designed to capture solar energy during the day and dispatch electricity into the grid during periods of high-value demand in the evenings. We look forward to keeping investors updated as construction advances on the pathway to first generation in 2028.
$FHE
Further coverage of Friday's sod turning ceremony and major construction commencing at our Stage One Waroona Renewable Energy Project on @7NewsAustralia 📺
When energy generation commences in 2028, Waroona will become the largest solar and battery hybrid facility connected to WA’s main electricity network and will be a major part in helping the State reach its target of 75% renewable energy by 2031.
$FHE
4
212
A sod turning ceremony held on Friday marked the start of major construction at our Waroona Renewable Energy Project Stage One in Western Australia, a day our team has worked towards for more than five years and a significant milestone for Frontier $FHE.
Hear @StockheadAU presenter Tylah Tully discuss in the video below 📺
If you missed today's announcement, you can read it here: loom.ly/V3tQ5jw
3
287
Major construction has commenced at our Stage One Waroona Renewable Energy Project in Western Australia: loom.ly/V3tQ5jw
The commencement of construction was marked by a Sod Turning Ceremony, led by The Honourable Amber-Jade Sanderson MLA, Western Australia’s Minister for Energy and Decarbonisation as well as The Honourable Josh Wilson MP, Federal Assistant Minister for Climate Change and Energy. Also in attendance were major investors, Frontier directors, and representatives from various groups, including the Shire of Waroona, EPC contractors, Western Power and other key stakeholders.
$FHE CEO Adam Kiley @Soph_Investor said: “This marks the start of major construction at Stage One, a day our team has worked towards for more than five years and we are proud to reach this important milestone.
“When energy generation commences in 2028, our Waroona Project will become the largest solar and battery hybrid facility connected to WA’s main electricity network and will be a major part in helping the State reach its target of 75 per cent renewable energy by 2031.
“Stage One is only the beginning for Frontier, as we aim to expand beyond Stage One and establish the Waroona Project as a major renewable energy hub in the heart of South West WA, bringing much-needed new generation onto the grid in an area that has been supported by coal for more than 60 years.”
⚡ Developing Western Australia's largest hybrid solar and battery project | Frontier Energy $FHE is discussed on @7NewsAustralia, following major construction commencing at our Waroona Renewable Energy Project this week.
Watch below 📺
Emerging player Frontier Energy $FHE has broken ground on its $310m South West renewables project, writes journalist Hayley Primmer in the @WestAustralian.
In the below article, our CEO Adam Kiley @Soph_Investor highlights that our flagship Waroona Renewable Energy Project will be essential in retiring WA’s reliance on coal powered resources, and that Stage One alone will replace a third of the power generated by the Collie power station, set to permanently close in 2027.
“Today when it’s 6 o’clock in the evening, it’ll be largely coal and gas powering the state,” he said. “Fast forward two years when this project is up and going, we’re going to be a big part of helping replace that because of the sun shining.”
He said initial work will make a meaningful contribution to the foundations for the State’s energy transition, and discusses the expansion on the horizon for Frontier after Stage One’s expected completion in mid-2028.
Energy Minister Amber-Jade Sanderson MLA, who attended the official sod-turning ceremony held on Friday, said that Waroona had the State Government’s full support.
📰 Read the full article: thewest.com.au/business/rene…
⬇️
.@FrontierASX $FHE has cleared another key hurdle to financial close of a $280m debt facility for Stage One of its Waroona renewable #energy project in WA, signing a federal revenue support agreement.
stockhead.com.au/energy/fron…
63
We have executed the Capacity Investment Scheme Agreement with the Australian Government in relation to Stage One of the Waroona Renewable Energy Project in Western Australia: loom.ly/sGPTfBg
Our Executive Chairman Jamie Cullen commented: “This is yet another major milestone for Frontier in 2026. The execution of the CISA means there are no major conditions precedent remaining on the $280m debt facility, meaning financial close will take place shortly.
"We would again like to thank the Australian Government for this important initiative in supporting renewable energy generation and storage across the country. The support provided under the Capacity Investment Scheme was a key factor in Frontier securing its $280m debt facility.
"We now look forward to welcoming members from the Australian and WA State Governments to site on 13 November 2026 for the official Sod Turning ceremony to mark the official start of major construction at the Project.”
Watch our latest video update below which provides an overview of the Waroona Renewable Energy Project 📺
$FHE #Waroona #RenewableEnergy
We have executed the Syndicated Facility Agreement for project finance debt facilities of up to A$280m, provided by a syndicate of international lenders led by Natixis CIB and Sumitomo Mitsui Banking Corporation. Execution of the SFA is one of the final steps towards financial close of the Debt Facilities, which is expected to occur in November.
Our Executive Chairman Jamie Cullen said: “Execution of the SFA is a major milestone for Frontier and comes as site works at Stage One are ramping up. We would like to thank Azure Capital, the Company’s debt finance advisor, as well as the syndicated lending consortium that has committed the funding for developing Stage One, a major renewable energy project for Western Australia.
"With the SFA executed and financial close on track to occur during November, construction activities at our Waroona Project are ramping up, whilst we also continue to work through future expansion opportunities.”
Read more: loom.ly/Y6ATCVs
$FHE
During the September quarter, mobilisation to site commenced at our Waroona Renewable Energy Project in WA, marking the transition from several years of development to the construction phase of Stage One. With Monford having mobilised to site, early works are under way.
Work carried out to date includes establishment of the construction laydown area, installation of construction facilities, tree clearing within the 330Kv under cable route, commencement of topsoil removal bulk earthworks for the solar farm’s internal road network, and construction of the operation and maintenance compound pad.
The first shipment of ~5,000 Tracker Piers has been dispatched and is scheduled to arrive in Fremantle in mid-November. Major construction works will begin later this year and will include field piling for installation of the single access tracking system, before moving on to installation of the photovoltaic modules and construction of the solar facility balance of plant, which is scheduled to commence in early 2027.
Read more about the progress on site in our September 2026 Quarterly Report: loom.ly/aB0pc4E
$FHE
📺 @Stockhead Presenter Tylah Tully provides an overview of our latest announcement, following an increase in Reserve Capacity Credits allocated to Stage One of our Waroona Renewable Energy Project in Western Australia.
The Australian Energy Market Operator (@AEMO_Energy) has increased the project's annual RCC allocation from ~88MW to 99MW, lifting forecast annual fixed capacity payments from ~$32m to ~$36m.
The increased allocation strengthens the project's financial outlook, with average annual revenue now forecast at $76m, EBITDA of $66m and free cash flow of $38m through to September 2032, based on first generation commencing in mid-2028.
Read more: loom.ly/UtYnLrw & watch below ⬇️
3
94
The Australian Energy Market Operator (@AEMO_Energy) has increased the Reserve Capacity Credits (RCCs) allocated to Stage One of our Waroona Renewable Energy Project from ~88MW to 99MW.
The increase in RCCs lifts the annual Reserve Capacity Payment (RCP) received by Frontier to ~$36m (previously ~$32m). We have updated our average annual forecasts for Stage One for the period from first generation to 30 September 2032:
✅ Average annual Revenue ~ $76m (up from $~72m)
✅ Average annual EBITDA ~ $66m (up from ~$62m)
✅ Average annual Free Cash Flow ~ $38m (up from $35m)
Revenue received from RCCs is in addition to revenue received from energy sales.
Read the full announcement here: loom.ly/dwtqwrM
$FHE
Frontier $FHE has progressed Stage Two of its Waroona Renewable Energy Project, with Western Power deeming it ‘Ready to Progress’ under its Critical Projects Framework, advancing its pathway to grid connection.
Read more in @StockheadAU👇
stockhead.com.au/energy/fron…
We have reached a key milestone in the development of Stage Two of our Waroona Renewable Energy Project in Western Australia, with Western Power deeming the project ‘Ready to Progress’ under its Critical Projects Framework.
The designation recognises Stage Two as a project of strategic importance and provides greater certainty around progressing its connection to the South West Interconnected System (SWIS).
Waroona’s Stage Two is planned to comprise a 130MW solar generation facility paired with an 80MW (~8-hour) battery energy storage system (BESS), building on infrastructure already being developed as part of Stage One, where site works commenced in September.
Our Executive Chairman Jamie Cullen said: “Being deemed Ready to Progress is a key milestone in the development process and recognises the strategic significance of Stage Two.
“With a sizeable landholding and ability to cost-effectively access the SWIS, the development of Stage Two is central to our strategy to establish the Waroona Project as a major renewable energy hub in Western Australia’s South-West region.”
Read more: loom.ly/jb2CPIk
$FHE
Our CEO Adam Kiley @Soph_Investor sat down with @CruxInvestor’s Matthew Gordon last week to discuss the latest developments at our Waroona #RenewableEnergy Project in WA, where mobilisation works recently commenced.
The current program underway will include establishment of the construction laydown area, installation of construction facilities, site preparation, clearing, earthworks and drainage works. The mobilisation program will then be followed by the commencement of major construction activities, including detailed earth works for internal access tracks in October and solar array piling commencing in December, before the first trackers and solar panels are installed in February 2027.
In the below clip, hear Adam walk through the Waroona Project's impressive economics, and the multiple revenue streams which will drive strong EBITDA.
Watch the full $FHE interview: loom.ly/JY-zcQo
Following mobilisation works commencing at our Waroona Renewable Energy Project in Western Australia, Frontier CEO Adam Kiley @Soph_Investor caught up with @CruxInvestor's @MoshiGordon to provide an update on the company's recent progress and momentum.
📺 Watch the interview here: loom.ly/JY-zcQo
"Frontier Energy $FHE has crossed the threshold that separates most renewable energy developers from the small number that actually get built: it is fully funded, fully contracted, and now has boots on the ground," the Crux team wrote – read more: loom.ly/WTmxnWE
67