Washington/Wilkinson counties: Crews are preparing to begin an ITB project on State Route 57 at the Oconee River (Balls Ferry). Approach slabs will be replaced on both sides of the bridge. Work is scheduled to start on Monday, November 9.
1
80
A continuous, 24/7 lane closure will be implemented. SR 57 will be a one-lane road through the work zone. Traffic will be controlled using a portable traffic signal. Weather permitting, this project is expected to take about two months. Use caution when navigating the area.
30
🚨 Heads Up, Drivers! Motorists traveling to or through Metro Atlanta should plan ahead for scheduled weekend closures associated with the I-285 Rebuild project along the west side of the interstate. 🚧 ➡️ Visit 511ga.org to plan your route and check for updates
1
99
Burke County: The new bridge on Quaker Road at Beaver Dam Creek is open to traffic!
4
138
Newton County: SR 11 & SR 142 is now a roundabout configuration! Continue using causing when navigating the area. The project is not over. Crews will continue working on site. Remaining tasks include construction of the center island, truck aprons, and curbs.
3
97
Newton County: SR 11 & SR 142 is scheduled to be changed to a roundabout configuration today! (10/20)
1
1
5
164
The Georgia Department of Transportation recently awarded new contracts for projects in the agency’s east-central district.
1
1
162
In Jefferson County, Reeves Construction Company has been awarded a $1.08 million project to make safety enhancements on Zebina Rd., between Middle Ground Rd. and Washington St. The project will add new striping, signage, and raised pavement markers to the route.
1
57
Additionally, the shoulder will be widened by two feet. A completion date of August 31, 2027 has been given.
31
Wilkes/Warren/McDuffie counties: The new bridge on State Route 80 at Little River is OPEN! Thank you to our contractor E.R. Snell for building the bridge and reopening the road two months ahead of schedule!
3
144
Help us congratulate and wish good luck to Charlie Davis! He qualified to compete in this year’s Southeastern Regional Equipment Operator Safety Training Conference and Roadeo! He will put his skills to the test against other single axle truck operators from across the region.
6
153
Progress continues on the State Route 44 widening projects. Crews on the Phase 1 project have started putting down graded aggregate base. Crews are also working to widen the existing bridge over I-20. Clearing continues on the Phase 2 project.
3
116
Newton County: Work is resuming on our roundabout project at SR 11 and SR 142! The contractor was ready to pave in May, but paving was delayed until the utility company finished relocating poles. Now that they have been relocated, the contractor will regrade to prepare to pave.
2
116
The Georgia Department of Transportation recently awarded new contracts for projects in the agency’s east-central district.
1
126
In Laurens County, Reeves Construction Company has been awarded a $2.84 million project to resurface more than four miles of State Route 31/US 441/US 319, between Interstate 16 and State Route 26/US 80. A completion date of July 31, 2027 has been given.
1
67
Peek Pavement Marking, LLC has been awarded a $767 thousand project to make signage and pavement marking upgrades at various railroad crossings in Burke, Glascock, Jefferson, Jenkins, Richmond, and Warren counties. A completion date of July 31, 2027 has been given.
41