True phenomenon however at today’s rental rates a 3 yr lease generates enough levered FCF to pay off a 5 yr data center term. 1 yr of operating a GPU fleet with no debt service adds the ability to pay for another 3 years of data center lease time.
Structuring is key.
Prepayment % has a 1:1 inverse correlation with the loan to value (LTV)
LTV has a 1:1 direct correlation with the DSCR on a specific GPU cluster (dictated by the hourly rate vs the cost of the server)
LTVs right now: 55-70%
DSCRs right now: 1.15-1.3
🔄
When you can make $30/hr selling inference, a lot of people are willing to absorb lower margins for compute that does not require prepayments.
If you can pay prepayments, your cost is dramatically lower.
Welcome to the credit crunch!
3
213
Stand up a high availability gpu cluster and show me the uptime telemetry. Then you are allowed to call it a commodity. Most neoclouds will fail on execution because these are hard to build and not commodities that capital alone solves.
Watch how many neoclouds go bankrupt.
I knew these were atrocious businesses. They’re financial companies in a commoditized sector.
2
6
360
This report should be mandatory reading for everyone building:
1. compute marketplaces
2. gpu futures trading
3. compute interoperability / managed services
I agree AI is more useful yada yada but tell me you don’t see the similarities. Enron literally had all of these products for broadband.
datacenterdynamics.com/en/an…
Nice purpose built for VR200s! Getting 800 VDC transformers hasn’t been easy. Hopefully they can bring production online and are actually willing to sell to others
3
210
👀 hmm
Exclusive: Amid a server shortage, Anthropic has been asking where to find 5 to 10 MW of power in older buildings, as demand revives interest in decades-old telecom facilities.
Read more: thein.fo/4AjtXQm
1
171
It’s almost impossible to get 1-3MW colo right now. We’re building dark fiber and powered shell to extend Colo sites out to buildings with power and cooling in cities.
1
2
189
Small distributed sites are def the way. The challenge with Brightspeed sites that we’ve seen in the CLEC (old telephone sites) we’ve surveyed is that they don’t have the chilled water capacity you need for 7MW of liquid cooled chips.
1 - as soon as you need to roll in a new air cooled chiller unit you run into environmental permitting
2 - if you drop in air cooled B300s your PUE goes through the roof and you are probably at 2MW of critical IT
Still definitely the way forward vs large centralized sites.
Exclusive: Nvidia has submitted a proposal to Brightspeed, an Apollo-owned broadband provider reportedly nearing bankruptcy, to convert some of its 130-plus telecom buildings into AI data centers.
Nvidia estimates the sites have roughly 1 gigawatt of available power, potentially enough to run tens of billions of dollars of Vera Rubin chip systems.
Read more: thein.fo/4AjtXQm
2
152
The second order effect of the craziness in the compute market is that the lending markets have become insane and sometimes shady.
Seeing 35% IRR equipment lease deals or waterfall JVs get slung around by boutique banks who are sometimes hiding behind two levels of syndication. No transparency on fees with term sheets being offered in 24 hours and sometimes pulled just as quickly. If you're financing compute clusters in the 1-4MW range stay safe out there.
2
129
Talking about how many tokens your platform serves is like an ISP in 2005 talking about how many bytes of data it passed on its network.
1 - Will be abstracted away by newer pricing models that are all you can eat, with token caps that are too high to keep track (similar to ISPs throttling at high data caps)
2 - the volume of tokens is not as important as the type of models and workloads it was spent by
Standing up 18GW in two years and making compute 82% of cash flow would be epic. Wouldn’t bet against them but:
1 - They’d have to have all of that in construction now at sites not yet made known to the public 🧐
2 - Also curious where the debt line item sits in this
Over the last week I built a bottoms up SpaceX financial model through the end of 2028
The numbers that came out are insane
There are wide error bars given how quickly things are changing but I wanted to distill something complicated into something that can at least be debated
* This is not investment advice!!!
** Sequoia is a major SpaceX shareholder
*** Past performance is not indicative of future results
1
6
389
GPU clouds building 1-3MW clusters that can be turned up quickly with debt that amortizes in under 3 years can handle higher credit costs than the clouds building 30MW+ sites mainly due to time to RFS from drawing down on their loan. People will soon realize these are two different categories.
The middle market for compute financing ($10M to $300M) is alive and well.
This is what we’re seeing from our OEMs who are saying hey can ship B300s to us quickly. Priority is given to those who can install fast
Microsoft said that "some third-party GPU-as-a-service contracts have been delayed to the second half" of FY27, so calendar quarters Q1 and Q2 2027..
I wonder which "neocloud" contracted to deliver capacity to Microsoft in Q4-26 is running behind schedule..